- First output had been removed by NA (Analysis of Existing Situation & Road Map Reporting) 01-Nov-17 --> 15-Feb-18
(REASONING --> The analysis of the current situation, state of the art in the form of a compendium, is not eligible as intellectual production. This is a document of internally usable work for the design of training (O2).)
- Second output (Learning System Curriculum & Survey Questionnaire) 15-Feb-18 --> 30-Jun-18 MULTI
- Third output (Mentor Training System) 01-Jul-18 --> 30-Apr-19 MULTI
- Fourth output had been removed by NA (Guidelines Tool - Users' Manual) 01-Oct-18 --> 30-Apr-19, however partnership realized the output as it is essential for the proper implementation
(REASONING --> The exploitation guidelines for O2 and O3 intellectual productions do not constitute an intellectual production in their own right.)
- Fifth output had been removed by NA (Website Platform) 01-May-18 --> 30-Sep-19 MULTI, , however partnership realized the output as it is essential for the proper implementation
(REASONING --> The project website is not an intellectual production. It must be funded by the "Project Management and Implementation" line for communication purposes and sharing of results.)
- Sixth output had been removed by NA (Field Tests - Feedback Setup and Evaluations) 01-Feb-19 --> 15-Oct-19, however partnership realized the output as it is essential for the proper implementation
(REASONING --> The testing and evaluation of intellectual productions are not intellectual productions. Evaluation is part of the good management and implementation of the project.)